October 20, 2014
Key events
2004: PHASE A (selection of the instruments and feasibility finalizing)
2005: PHASE B (definition studies)
- 01/2005: Project Science Group Meeting Kick-off (PSGM)
- 12/01-12/02/2005: CHEMCAM Instrument Preliminary Design Review (IPDR)
- 03/06-03/07/2006: SAM Instrument Preliminary Design Review (IPDR)
2006-2010: PHASE C/D (development)
- 06/2006: MSL Preliminary Design Review (PDR)
- 05/01-05/03/2007CHEMCAM Instrument Critical Design Review (ICDR)
- 02/06-02/09/2007: SAM Instrument Critical Design Review (ICDR)
- 06/2007: MSL Critical Design Review (CDR)
- 11/2008: CHEMCAM and SAM Flight Model (FM) delivery to JPL
- 08/2010: MSL Mission Readiness Review (MRR)
11/25-12/18/2011: LAUNCH WINDOW
10/2011-08/2012: OPERATIONS TRAINING PHASE
08/2012: ARRIVAL AROUND MARS
08-11/2012: OPERATIONS PHASE AT JPL: 90 sols about 3 months
12/2012-12/2014: ROUTINE OPERATIONS PHASE: 2 years (extensible to 4 years)